Question: Abdullah, a project manager is identifying and documenting relationships among the project activities of an IT project. He is undertaking which of the following process?

Abdullah, a project manager is identifying and documenting relationships among the project activities of an IT project. He is undertaking which of the following process?

A. Define Activities B. Develop Schedule C. * Sequence Activities D. Estimate Activity Durations