Question: A project manager is identifying and documenting relationships among the project activities of an IT project. He is undertaking which of the following process? A.
A project manager is identifying and documenting relationships among the project activities of an IT project. He is undertaking which of the following process?
A. * Sequence Activities B. Define Activities C. Develop Schedule D. Estimate Activity Durations