Question: Omega 2 Project. Using the complexity weighting scheme shown in Table 5.2 and the following function point complexity weight table, estimate the total function point
Omega 2 Project. Using the “complexity weighting” scheme shown in Table 5.2 and the following function point complexity weight table, estimate the total function point count. Assume historical data suggest five function points equal one person a month and six people have been assigned to work on the project.
a. What is the estimated project duration?
b. If 20 people are available for the project, what is the estimated project duration?
c. If the project must be completed in six months, how many people will be needed for the project?
Number of inputs Number of outputs Number of inquiries Number of files Number of interfaces Complexity Weight Table 15 20 10 8 8 8 30 50 Rated complexity low Rated complexity average Rated complexity average Rated complexity average Rated complexity high
Step by Step Solution
3.40 Rating (163 Votes )
There are 3 Steps involved in it
The total function point count is Complexity Weightin... View full answer