Question: Firewall Project XT. Using the complexity weighting scheme shown in Exercise 5.3 and the function point complexity weighted table shown below, estimate the total function
-1.png)
a. What is the estimated project duration?
b. If 20 people are available for the project, what is the estimated project duration?
c. If the project must be completed in six months, how many people will be needed for the project?
Exercise 5.3
-2.png)
Complexity Weight Table Number of inputs Number of outputs 20 Rated complexity average Number of inquiries0Rated complexity average Number of files Number of interfaces 50 Rated complexity high 10 Rated complexity low 30 Rated complexity high Router systems project Cost: $600,000 Definition 1096 Design Implementation 50% 40% Objectives 4% Requirements 6% In-house testing 40% Customer testing & review 10% Irp Files Programming )% 3% 3% 4% 10%
Step by Step Solution
3.50 Rating (160 Votes )
There are 3 Steps involved in it
The total function point count is Complexity Weighting ... View full answer