Question: Task Z Duration: Pessimistic (P) = 60 Most Likely (M) = 40 Optimistic (O) = 32 Given Task Z estimates, calculate the
Task Z Duration:
• Pessimistic (P) = 60
• Most Likely (M) = 40
• Optimistic (O) = 32 Given Task Z estimates, calculate the activity duration:
A. 45 B. 54.5 C. 42 D. 40