Question: Task Z Duration: Pessimistic (P) = 60 Most Likely (M) = 40 Optimistic (O) = 32 Given Task Z estimates, calculate the

Task Z Duration:

• Pessimistic (P) = 60

• Most Likely (M) = 40

• Optimistic (O) = 32 Given Task Z estimates, calculate the activity duration:

A. 45 B. 54.5 C. 42 D. 40