Question: The project scope statement is decomposed into the work breakdown structure. The WBS then becomes an important part of the project for planning, execution, and

The project scope statement is decomposed into the work breakdown structure. The WBS then becomes an important part of the project for planning, execution, and control. A WBS serves as an input to many of the project processes. Of the following, which is not true?

A. WBS serves as an input to activity sequencing.

B. WBS serves as an input to activity definition.

C. WBS serves as an input to risk identification.

D. WBS serves as an input to cost budgeting.