Question: The project scope statement is decomposed into the work breakdown structure. The WBS then becomes an important part of the project for planning, execution, and


The project scope statement is decomposed into the work breakdown structure. The WBS then becomes an important part of the project for planning, execution, and control. A WBS serves as an input to many of the project processes. Of the following, which is not true?
A.
WBS serves as an input to activity sequencing.
B.
WBS serves as an input to activity definition.
C.
WBS serves as an input to risk identification.
D.
WBS serves as an input to cost budgeting.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management For Small Projects Questions!