Question: What should a project manager do if they identify additional work that needs to be included in the project? a) Add the work to the

What should a project manager do if they identify additional work that needs to be included in the project?

a) Add the work to the project scope immediately

b) Submit a change request for approval through the Perform Integrated Change Control process

c) Reject the additional work to avoid scope creep

d) Update the project charter