Question: Which process involves making necessary adjustments to project documents and plans to align with approved changes? a) Direct and Manage Project Work b) Monitor and
Which process involves making necessary adjustments to project documents and plans to align with approved changes?
a) Direct and Manage Project Work
b) Monitor and Control Project Work
c) Perform Integrated Change Control
d) Manage Project Knowledge