Question: You are a construction manager for a construction project. The project will be using a new material that the project team has never worked with

You are a construction manager for a construction project. The project will be using a new material that the project team has never worked with before. You allot $10,000 to train the project team on the new materials so that the project will operate smoothly. The $10,000 for training is known as what?

A. Cost of quality B. Cost of poor quality C. Sunk costs D. Contingency allowance Questions