Question: You are coaching several new project managers on effective control of stakeholder engagement. The project managers are confused as to why change requests come from
You are coaching several new project managers on effective control of stakeholder engagement. The project managers are confused as to why change requests come from this process. What is the most likely type of change that will come from controlling stakeholder engagements?
A. Technology change B. Errors or omissions in requirements C. External changes D. Corrective actions