Question: You are completing a group term paper.* Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify the
You are completing a group term paper.* Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify the critical path. Use this information to create a Gantt chart for the project. Be sure to show slack for noncritical activities.
Group Term Paper A Identify topic 1 Legend ES ID EF SL Description LS DUR LF B Research topic 5 Identify topic Research topic Draft paper Ede paper Create graphics References Proof Submit paper 0 Draft paper 3 2 6 D Edi paper 2 E Create graphics F References 1 10 12 09 Proof 14 G H Submit Paper 1
Step by Step Solution
3.39 Rating (158 Votes )
There are 3 Steps involved in it
Early start late start early finish late finish and slack are shown on the diagram above The ... View full answer