Question: Youve constructed the WBS for your recent project. Level two assignments have been made, and youve requested that the subproject managers report back to you
You’ve constructed the WBS for your recent project. Level two assignments have been made, and you’ve requested that the subproject managers report back to you in 3 weeks with each of their individual WBSs constructed. All of the following are true except:
A. The work package level facilitates resource assignments.
B. The work package level is the lowest level in the WBS.
C. The work package level defines the agreed-upon deliverables.
D. The work package level facilitates cost and time estimates.