Question: Youve constructed the WBS for your recent project. Youve requested that the subproject managers report to you in three weeks with each of their individual

You’ve constructed the WBS for your recent project. You’ve requested that the subproject managers report to you in three weeks with each of their individual WBSs constructed.

Which statement is not true regarding the subproject managers’ WBS?

A. The work package level is decomposed to create the activity list.

B. The work package level is the lowest level in the WBS.

C. The work package level facilitates resource assignments.

D. The work package level facilitates cost and time estimates.