Question: Develop the network activity chart and identify the critical path for a project based on the following information. Redraw the activity network as a Gantt

Develop the network activity chart and identify the critical path for a project based on the following information.

Redraw the activity network as a Gantt chart. What is the expected duration of the project?

Activity Expected Duration Predecessors ABCDEFGH 5 days 6 days A 2 days

Activity Expected Duration Predecessors ABCDEFGH 5 days 6 days A 2 days A 4 days A 6 days B, C 6 days D, E 12 days F 4 days G 6 days F J 7 days H, I