Question: Given the project in Problem 27, simulate the completion of the project 1000 times, assuming that the activity times are at the 99 level and

Given the project in Problem 27, simulate the completion of the project 1000 times, assuming that the activity times are at the 99 level and follow a triangular distribution. LO6

(a) Determine the probability of each path becoming the critical path.

(b) What is the probability that the project is completed in 32 days? In 34 days? In 38 days?

(c) How do your answers compare with your answers in Problem 27?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management Questions!