Question: Using the data for Exercise 13.36, add the resource assignments to each of the activities and input their hourly rates as shown. Construct an earned
Using the data for Exercise 13.36, add the resource assignments to each of the activities and input their hourly rates as shown.
Construct an earned value chart for the project. Which activities have negative variances? What is the estimate at completion
(EAC) for the project? (Hint: Remember to click “Set baseline”
prior to creating the EVM table. This table is found by clicking on the “View” tab, then “Tables,” then “Other Tables.”)

Resource Name Hourly Rate ($) Josh 12.00 Mary 13.50 Evan 10.00 Adrian 22.00 Susan 18.50 Aaron 17.00 Katie 32.00
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
