Question: Using the data in the table below, complete the table by calculating the cumulative planned and cumulative actual monthly budgets through the end of June.

Using the data in the table below, complete the table by calculating the cumulative planned and cumulative actual monthly budgets through the end of June. Complete the earned value column on the right. Assume the project is planned for a 12-month duration and a $250,000 budget.

Activity Jan Feb Mar Apr May Jun Plan % Comp. Value Staffing

Activity Jan Feb Mar Apr May Jun Plan % Comp. Value Staffing 8 7 15 100 Blueprinting 4 Prototype 62 6 10 100 2 8 10 70 3 2 8 - 14 - 9 - | | | 6 Development Full Design Construction Transfer Monthly Plan Cumulative Monthly Actual Cumul. Actual - 10 - 15 - - 10 30 10 220 21 60 32 25 10 | | | | | | 40 I

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To solve the problem we will calculate the monthly planned values cumulative planned values monthly actual expenses cumulative actual expenses and ear... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management Questions!