Question: Using the data in the table below, complete the table by calculating the cumulative planned and cumulative actual monthly budgets through the end of June.
.png)
Activit Staffing Blueprinting Prototype Jan Feb Mar Apr May Jun Plan %C Value 15100 10 100 Development Full Design Construction Transfer 10 70 10 21 67 2 30 32 25 10 10 0 Monthly Plan Cumulative Monthly Actual Cumul. Actual 10 15 6 14 9 40