Question: A critical path network diagram does not ____ A. Help determine the amount of float. B. * Calculate how much work has been done. C.

A critical path network diagram does not ____ A. Help determine the amount of float.

B. * Calculate how much work has been done.

C. Identify the particularly important activities.

D. Calculate the duration of the whole project.