Question: A critical path network diagram does NOT A. Identify the particularly important activities. B. Calculate the duration of the whole project. C. * Calculate earned

A critical path network diagram does NOT A. Identify the particularly important activities.

B. Calculate the duration of the whole project.

C. * Calculate earned value.

D. Help determine the amount of float.