Question: A generally accepted method to confirm accuracy of task progress is through: (a) Earned value (b) Probability versus outcome (c) Maximum ceiling (d) Work breakdown

A generally accepted method to confirm accuracy of task progress is through:

(a) Earned value

(b) Probability versus outcome

(c) Maximum ceiling

(d) Work breakdown structure