Question: A project is estimated to cost $ 50,000 with a timeline of 50 days. After 25 days, the project manager finds that 50% of the
A project is estimated to cost $ 50,000 with a timeline of 50 days.
After 25 days, the project manager finds that 50% of the project is complete and Actual costs are $ 50,000. What is the Cost Performance Index (CPI)?
A. The CPI is 1 B. The CPI is 1.5 C. * The CPI is 0.5 D. The CPI is 2
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
