Question: A project manager has discovered that a project is outside the original scope. The project manager has requested a change to bring expected future performance

A project manager has discovered that a project is outside the original scope. The project manager has requested a change to bring expected future performance of the project work back in line with the project management plan. What type of change implementation has the project manager requested?

A. * corrective action B. defect repair C. lessons learned D. preventive action