Question: A project manager is trying to complete a software development project, but cannot get enoughattention for the project. Resources are focused on completing process-related work,

A project manager is trying to complete a software development project, but cannot get enoughattention for the project. Resources are focused on completing process-related work, and the projectmanager has little authority to assign resources. What form of organization must the project managerbe working in?

A. * Functional B. Matrix C. Expediter D. Coordinator