Question: ABC Tiles contracted to install ceramic tile in a 4floor office building, with a typical floor area of 4250 square feet. The contract stipulates that
ABC Tiles contracted to install ceramic tile in a 4‐floor office building, with a typical floor area of 4250 square feet. The contract stipulates that the work must finish in 34 days at a cost of $5/ft2.
A What are the project’s cost and schedule baselines?
B Assuming linearity in work, what are the daily planned production and budget?
C After 5 days, the crew finished 4100 ft2 at a cost of $15,220. What is the status of the project?
D Would you change your mind on the status of the project, part
c, if you learned that the crew worked only on rooms (open spaces) and have not started any of the bathrooms and kitchens? What does this tell you regarding project controls?