Question: according to the network diagram given here, find the minimum duration required to complete the project A. * 16 days B. 10 days C. 26
according to the network diagram given here, find the minimum duration required to complete the project A. * 16 days B. 10 days C. 26 days D. 7 days
Step by Step Solution
There are 3 Steps involved in it