Question: 5. (4 points) Using the network of question 2, the minimum time required to complete the project is: A. 23 days B. 24 days C.
5. (4 points)
Using the network of question 2, the minimum time required to complete the project is:
A. 23 days
B. 24 days
C. 29 days
D. 31 days
E. None of the above
6. (3 points)
Using the network of question 2, the slack at activity E is:
A. 0
B. 5
C. 6
D. 13
E. None of the above

Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
