Question: 5. (4 points) Using the network of question 2, the minimum time required to complete the project is: A. 23 days B. 24 days C.

5. (4 points)

Using the network of question 2, the minimum time required to complete the project is:

A. 23 days

B. 24 days

C. 29 days

D. 31 days

E. None of the above

6. (3 points)

Using the network of question 2, the slack at activity E is:

A. 0

B. 5

C. 6

D. 13

E. None of the above

5. (4 points) Using the network of question 2,

D58D = NetworkQ2_6Sp20-1 [Compatibility Mode] Q Search in Document Home Insert Design Layout References Mailings Review View 3+ Share Times New R... 12 - AA- A- A T ARX AaBbce de Aah Celdre AaBb CeNdEc AaBbc dee AaBbCeDdE B IV.abe X, X Paste MARCADA A Emphasis Heading 1 Normal Strong Subtitle Styles Pano EZ B. 8 AS F.2 H,6 G4 D,8 2.(4 pints) A network showing the sequence of activities that must be performed to complete a project is given in the Word file in the Final Examination Session under Lessons. The carly start time (ES) for job G is: A. 13 B. 19 C. 21 D. 25 E. 38 3. (6 points) Using the network of question 2, the late finish time (LF) for job B is A. 13 B. 14 C. 16 D. 19 E. 22 4.(4 points) Using the network of question 2, the critical path is given by: A. A 13 H BABETH CA+B-FG-H DAD-FH E.AC+F G H Page 1 of 2 200 words LY English (United States) E ---+ 120%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!