Question: An employee has been asked to evaluate a project that is experiencing some performance challenges. She asked the project manager to call a meeting with
An employee has been asked to evaluate a project that is experiencing some performance challenges. She asked the project manager to call a meeting with the project sponsor. The project manager replies that he does not know who the project sponsor is. The employee decides to review the initial project document. Which document should she request?
A. business case B. project baseline document C. * project charter D. project plan