Question: Slack time in project management is : A. The latest point in time when the schedule activity can begin so as not to delay the

Slack time in project management is :

A. The latest point in time when the schedule activity can begin so as not to delay the project completion date or any constraint.

B. * time a task can be delayed without causing another task to be delayed, or without impacting the overall project completion C. The earliest point in time when the schedule activity can begin D. The earliest point in time when the schedule activity can complete