Question: An inter-task dependency in which two tasks must finish at the same time is called : A. Start-to-finish (FS) B. Finish-to-start (FS) C. * Finish-to-finish
An inter-task dependency in which two tasks must finish at the same time is called :
A. Start-to-finish (FS)
B. Finish-to-start (FS)
C. * Finish-to-finish (FF)
D. Start-to-start (SS)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts