Question: Analogous cost estimating: A. Integrates bottom-up estimating techniques with relevant statistical relationships to estimate the cost of the current project. B. * Relies on the
Analogous cost estimating:
A. Integrates bottom-up estimating techniques with relevant statistical relationships to estimate the cost of the current project.
B. * Relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project.
C. Is used most frequently in the later phases of a project.
D. Summarizes estimates for individual work packages to estimate the cost of the current project.