Question: Analogous duration estimating is: A. * Frequently used to estimate project duration when there is a limited amount of detailed information about the project. B.

Analogous duration estimating is:

A. * Frequently used to estimate project duration when there is a limited amount of detailed information about the project.

B. A bottom-up estimating technique.

C. Based on multiple duration estimating.

D. Generally more accurate than other duration estimating methods when expert judgment is used.