Question: BAC = 200PV = 100AC = 120EV = 80Assuming that future work will be performed at an efficiency rate that considers both the cost and

BAC = 200PV = 100AC = 120EV = 80Assuming that future work will be performed at an efficiency rate that considers both the cost and schedule performance indices because project schedule is a factor that impacts future effort, the estimate at completion (EAC) is:

A. 250.

B. 300.

C. 350.

D. * 345