Question: BAC = 200PV = 100AC = 120EV = 80Assuming that future work will be performed at an efficiency rate that considers both the cost and
BAC = 200PV = 100AC = 120EV = 80Assuming that future work will be performed at an efficiency rate that considers both the cost and schedule performance indices because project schedule is a factor that impacts future effort, the estimate at completion (EAC) is:
A. 250.
B. 300.
C. 350.
D. * 345