Question: BAC = 200PV = 100AC = 120EV = 80Your sponsor specifies that there is no additional money in the budget for your project and asks
BAC = 200PV = 100AC = 120EV = 80Your sponsor specifies that there is no additional money in the budget for your project and asks you to complete the project at the original budget at completion (BAC). To achieve that goal, you and your team must complete the remaining work at the to-complete performance index (TCPI) of:
A. 0.67.
B. 1.00.
C. * 1.50.
D. 2.00.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts