Question: Chandler is setting up a time schedule for beta testing a new software project. Currently, the company has one computer lab compatible with his new

Chandler is setting up a time schedule for beta testing a new software project. Currently, the company has one computer lab compatible with his new program, and there are three other software programs being tested on that lab’s systems. Chandler modifies the timeline to account for sharing the computer systems. He is using which schedule analysis tool?

A. critical path method B. * critical chain method C. reserve analysis D. schedule compression