Question: Constructive changes are: A. Postponed as long as possible to protect the budget. B. Viewed as negative, quantified, and tabulated. C. * Uniquely identified and
Constructive changes are:
A. Postponed as long as possible to protect the budget.
B. Viewed as negative, quantified, and tabulated.
C. * Uniquely identified and documented by project correspondence.
D. Submitted for bids to the relevant vendor list.