Question: Constructive changes are: A. Postponed as long as possible to protect the budget. B. Viewed as negative, quantified, and tabulated. C. * Uniquely identified and

Constructive changes are:

A. Postponed as long as possible to protect the budget.

B. Viewed as negative, quantified, and tabulated.

C. * Uniquely identified and documented by project correspondence.

D. Submitted for bids to the relevant vendor list.