Question: Critical path method helps to find out which activities have float, and can be delayed without delaying the project schedule. Critical path has zero float,
Critical path method helps to find out which activities have float, and can be delayed without delaying the project schedule. Critical path has zero float, so the activities on the critical path should not be delayed. Float makes the project work flexible . One of the below options is not a valid float, identify it.
A. Free float.
B. Product float.
C. Total float.
D. Project float.