Question: During project executing, a project team member informs the project manager that a work package has not met the quality metric, and that she believes
During project executing, a project team member informs the project manager that a work package has not met the quality metric, and that she believes it is not possible to meet it. The project manager meets with all concerned parties to analyze the situation. Which part of the quality management process is the project manager involved in?
A. Manage Quality B. Perform Integrated Change Control C. * Control Quality D. Plan Quality Management