Question: During the Earned Value Analysis manager has found earned value is equal to actual cost. What does it mean? A. CPI is infinity B. Project
During the Earned Value Analysis manager has found earned value is equal to actual cost. What does it mean?
A. CPI is infinity B. Project is under budget and on schedule C. * There is no cost variance D. CPI = 0