Question: Earned value (EV) involves all of the following EXCEPT: A. Value of the work performed expressed in terms of the budget authorized for that work.
Earned value (EV) involves all of the following EXCEPT:
A. Value of the work performed expressed in terms of the budget authorized for that work.
B. * Actual cost for an activity or work breakdown structure (WBS)
component.
C. Progress measurement criteria, which should be established for each WBS component to measure work in progress.
D. Budget associated with the authorized work that has been completed.