Question: Eugene is the key stakeholder as well as the project manager in the project. She is working on some of processes available in project stakeholder

Eugene is the key stakeholder as well as the project manager in the project. She is working on some of processes available in project stakeholder management. Currently she is working on a classification model in stakeholder analysis based on the power, urgency and their involvement in the project. This model is known as?

A. Power/interest grid.

B. Power/influence grid.

C. Influence/impact grid.

D. Salience model.