Question: Funding requirements for a project are usually in incremental amounts that are not continuous, and these appear as a step function in the graph depicting
Funding requirements for a project are usually in incremental amounts that are not continuous, and these appear as a step function in the graph depicting Cash flow, Cost baseline and Funding. Any gap at the end of the project, between the funds allocated and the cost baseline represents:
A. Charting error B. * Management reserves C. Contingency reserves D. Cost variance