Question: Glenn is determining the project cost baseline by calculating the costs approved for each of the projects work packages. Glenn is determining the: A. actual

Glenn is determining the project cost baseline by calculating the costs approved for each of the project’s work packages. Glenn is determining the:

A. actual cost.

B. cost variance.

C. earned value management.

D. * planned value.