Question: Greg is a Project Manager of a construction project. The customer has requested that an additional room needs to be constructed at an extra cost?
Greg is a Project Manager of a construction project. The customer has requested that an additional room needs to be constructed at an extra cost? How should Greg respond to this request A. * Document the request and present it to Change Control Board B. Refuse the request as this was not part of the original scope C. Accept the request as the customer is willing to pay for it D. Consult the project sponsor