Question: If a project has 5 days of project float and 10 days of total float, what will happen if the early start date is delayed
If a project has 5 days of project float and 10 days of total float, what will happen if the early start date is delayed 3 days, how will this impact the project completion date:
A. The project end date will be pushed out 5 days B. The project end date will be pushed out 10 days C. * The finish date won’t change D. The project will be able to finish early