Question: If a project has 5 days of project float and 1 0 days of total float, what will happen if the early start date is

If a project has 5 days of project float and 10 days of total float, what will happen if the early start date is delayed 3 days, how will this impact the project completion date:
Question 4Select one:
A.
The project end date will be pushed out 5 days
B.
The project end date will be pushed out 10 days
C.
The finish date won't change
D.
The project will be able to finish early