Question: If the cost variance is positive and the schedule variance is also positive, this indicates the: A. Project is under budget and behind schedule B.
If the cost variance is positive and the schedule variance is also positive, this indicates the:
A. Project is under budget and behind schedule B. Project is over budget and behind schedule C. * Project is under budget and ahead of schedule D. Project is over budget and ahead of schedule