Question: In project development, schedule information, such as who will perform the work, where the work will be performed, activity type, and WBS classification, are examples
In project development, schedule information, such as who will perform the work, where the work will be performed, activity type, and WBS classification, are examples of-
A. * Activity attributes B. Constraints C. Data in the WBS repository D. Refinements