Question: in project management, the term slack refers to the amount of time A. to complete an activity without delaying the project B. * an activity

in project management, the term slack refers to the amount of time A. to complete an activity without delaying the project B. * an activity can be delayed without delaying the project C. needed to complete the entire project D. required to complete the project’s critical activities